2 production operations mgmt problems

Details below and I will also upload: 

 

Submit one Excel file. Put each problem result on a separate sheet in your file. 

Problems FROM THE TEXTBOOK: (do the ones highlighted in yellow)

3.10 The activities needed to build a prototype laser scanning

machine at Dave Fletcher Corp. are listed in the following

table. Construct an AON network for these activities.

                       

ACTIVITY                

IMMEDIATE

PREDECESSOR(S)

ACTIVITY

IMMEDIATE

PREDECESSOR(S)

A

E

B

B

F

B

C

A

G

C, E

D

A

H

D, F

 

PREDECESSOR(S) ACTIVITY

IMMEDIATE